ASF – Insurance and Pension Funds Supervisory Authority
ASF – Insurance and Pension Funds Supervisory Authority
Intervention: Critical load protection with extended runtime
The client needed to ensure power continuity for an office building and its server infrastructure, both of which support critical loads and have demanding availability requirements.
The solution was divided into two independent systems: an 80 kVA UPS to protect servers and communications for approximately 120 minutes, and a 30 kVA UPS configured to support the remaining critical loads for approximately 180 minutes.
The installation was also integrated with the building’s existing generator. This combination maintains a stable power supply during grid failures and provides sufficient time for the generator to start or for the technical team to respond. The result is a more resilient infrastructure with extended runtime, a lower risk of interruption and improved protection for systems that are essential to operations.